What's in a typical FAI
- Ballooned drawing: every characteristic numbered
- Part accountability: part number, revision, serial or lot
- Material and special-process certs (heat treat, plating, passivation)
- Characteristic results: nominal, tolerance, actual measurement, pass/fail
- Inspection methods and equipment used (CMM, optical, gauges)
- Approval signatures
When you need an FAI
For a new part number, a drawing revision, a change in process, material source, or location, or after a long production gap.
FAI vs. PPAP
FAI proves the first part is right. PPAP (Production Part Approval Process) is a larger package that proves the process will keep producing it right, with capability studies, process flow, and control plans.